The month of February involves forming our tower level 37 and upwards. Formwork and windows have been the primary activities as we continue to build the structure of the building while enclosing it. Suite finishing is also underway with drywall installation ongoing on the 14th floor. Residents are asked to be mindful of the ongoing concrete, rebar, window, and equipment deliveries along Dundas St. and Bond St. Please exercise caution and be aware of traffic.
Project Update #20 – February, 2024

Jan 29, 2024