Project Update #28 – October 2024

Project Update #28 – October 2024

The month of October involves completing the structural steel and windows for the Mechanical Penthouse. Suite finishing is underway with drywall installation ongoing on the 51st floor, tiles on the 36th floor, painting on the 38th floor and kitchens on the 35th floor....

Project Update #27 – September 2024

Project Update #27 – September 2024

The month of September involves erecting the structural steel and windows for the Mechanical Penthouse. Suite finishing is underway with drywall installation ongoing on the 49th floor, tiles on the 26th floor, painting on the 27th floor and kitchens on the 26th floor....

Project Update #26 – August 2024

Project Update #26 – August 2024

The month of August involves erecting the structural steel for the Mechanical Penthouse and building envelope. Structural Steel and Windows have been the primary activities as we continue to build the top floors of the building while finishing it. Suite finishing is...

Project Update #25 – July 2024

Project Update #25 – July 2024

The month of July involves erecting the structural steel for the Mechanical Penthouse and building envelope. Structural Steel and Windows have been the primary activities as we continue to build the top floors of the building while finishing it. Suite finishing is...

Project Update #24 – June 2024

Project Update #24 – June 2024

The month of June involves completing the structural work. Formwork and windows have been the primary activities as we continue to build the structure of the building while enclosing it. Suite finishing is also underway with drywall installation ongoing on the 33th...

Project Update #23 – May 2024

Project Update #23 – May 2024

The month of May involves forming our Mechanical Penthouse and Roof. Formwork and windows have been the primary activities as we continue to build the structure of the building while enclosing it. Suite finishing is also underway with drywall installation ongoing on...

Project Update #22 – April 2024

Project Update #22 – April 2024

The month of April involves forming our tower level 49 and upwards. Formwork and windows have been the primary activities as we continue to build the structure of the building while enclosing it. Suite finishing is also underway with drywall installation ongoing on...

Project Update #21 – March, 2024

Project Update #21 – March, 2024

The month of March involves forming our tower level 44 and upwards. Formwork and windows have been the primary activities as we continue to build the structure of the building while enclosing it. Suite finishing is also underway with drywall installation ongoing on...

Project Update #20 – February, 2024

Project Update #20 – February, 2024

The month of February involves forming our tower level 37 and upwards. Formwork and windows have been the primary activities as we continue to build the structure of the building while enclosing it. Suite finishing is also underway with drywall installation ongoing on...

Project Update #19 – January, 2024

Project Update #19 – January, 2024

The month of January involves forming our tower level 31 and upwards. Formwork and windows have been the primary activities as we continue to build the structure of the building while enclosing it. Suite finishing is also underway with drywall installation ongoing on...